TL;DR: Unlock smarter construction scheduling with the Syncfusion Blazor Gantt Chart, this blog shows you how to define and visualize task dependencies like Finish-to-Start (FS), Start-to-Start (SS), and more using the Predecessor property. You’ll learn to fine-tune task timing with offsets, manage complex parent-child relationships, track delays with baselines, and customize connector lines, taskbars, and tooltips for better clarity.
Managing construction projects requires precise coordination of tasks, teams, and timelines. A single misstep, like starting interior work before roofing is complete, can lead to costly delays. The Syncfusion Blazor Gantt Chart offers a powerful solution for visualizing and managing task dependencies, helping construction managers maintain control and clarity.
Why task dependencies matter in construction
Imagine building a community center: excavation, concrete pouring, framing, and inspections must follow a strict sequence. Syncfusion’s Gantt Chart simplifies this process by:
- Linking tasks visually (e.g., Survey Land → Pour Footings).
- Automatically adjusting schedules when delays occur.
- Keeping stakeholders aligned with real-time updates.
- Customizing visuals to highlight critical paths.
- Scaling to large projects with thousands of tasks.
- Seamlessly integrating into Blazor applications.
Common challenges and Syncfusion solutions
Effective scheduling in construction hinges on how task dependencies are managed. Syncfusion Blazor Gantt Chart simplifies this with features designed to coordinate teams, handle delays, and maintain clarity across complex project timelines.
Let’s now explore some common challenges in construction scheduling and how Syncfusion’s Blazor Gantt Chart addresses them.
| Challenge | Syncfusion solution |
| Task overlaps | Visualized dependencies enforce execution order |
| Material delays | Dependent tasks are rescheduled automatically |
| Subcontractor alignment | Live updates keep teams in sync |
| Stakeholder communication | Custom visuals highlight critical paths |
Understanding task dependencies in Gantt Charts
Task dependencies define the order in which tasks are executed in a Gantt chart, represented visually as connector lines between taskbars. Let’s discuss the dependency types for construction workflows with examples.
Dependency types
Syncfusion supports four dependency types, each suited to specific coordination needs:
Finish-to-Start (FS)
- Definition: Task B starts only after Task A finishes.
- Construction example: Cure Footings must be completed before Framing begins.
- Benefit: Prevents premature execution.
- Rendering: Connector line from the end of Task A to the start of Task B.

Start-to-Start (SS)
- Definition: Task B starts when Task A starts.
- Construction example: Foundation Formwork Setup starts after Excavation begins.
- Benefit: Enables efficient parallel scheduling.
- Rendering: Connector line from the start of Task A to the start of Task B.

Finish-to-Finish (FF)
- Definition: Task B finishes when Task A finishes.
- Construction example: Handover finishes after Security System Setup.
- Benefit: Aligns finishing stages for inspection readiness.
- Rendering: Connector line from the end of Task A to the end of Task B.

Start-to-Finish (SF)
- Definition: Task B finishes before Task A starts.
- Construction example: Plumbing must finish before HVAC Installation starts.
- Benefit: Supports shift-based operations.
- Rendering: Connector from the start of Task A to the end of Task B.

Hierarchical task relationships
Now, that we’ve explored the core dependency types, let’s look at how these relationships extend across different task levels, parent and child, within a construction project. This helps ensure phase-level coordination and task-level accuracy.
| Relationship | example | benefit |
| Parent–Parent | "Site Preparation" → "Framing" | Maintains phase sequencing |
| Parent–Child | "Foundation" → "Pour Footings" | Syncs parent progress with critical subtasks |
| Child–Child | "Electrical Wiring" → "Plumbing" | Manages task-level interdependence |
| Child–Parent | "HVAC Installation" → "Interior Work" | Aligns subtasks with phase milestones |
The image below illustrates the task relationships in the Gantt chart:

Dependency formats and offset values
Offsets provide fine control over scheduling by adding delays or leads to dependencies.
Offset types:
The Gantt Chart offers two offset types:
- Positive (+): Add delays to accommodate processes like concrete curing or material delivery (e.g., “+3d” for curing time).
- Negative (−): Enables task overlaps for efficiency, such as starting related tasks before their predecessors complete (e.g., “-1d” for parallel work).
Format examples:
Below are a few format examples:
- 9FS+3d: Install Roof starts 3 days after Install Steel Frame.
- 12SS: Plumbing starts with Electrical Wiring.
- 14FF+2d: Final Inspection finishes 2 days after HVAC Installation.
-
13SF: HVAC Installation starts after Plumbing finishes.

Task dependency offset in Gantt Chart
Visualizing delay impacts with baselines
Delays in construction, such as late material deliveries or adverse weather, can disrupt project schedules. The Syncfusion Blazor Gantt Chart’s baseline feature addresses this by displaying the planned schedule (gray taskbars) alongside the adjusted schedule (blue taskbars).
For example:
A delay in Pour Footings automatically shifts dependent tasks like Cure Footings and Framing, with connector lines updating dynamically to reflect the new timeline.
Configuring predecessors in Blazor Gantt Chart
In construction projects, tasks must follow a logical order. The Syncfusion Blazor Gantt Chart makes this easy by using the Predecessor property to link tasks with dependencies like FS, SS, FF, and SF.
For example:
Setting predecessor = 2FS+3d for the Install Roof task means it will start three days after Install Steel Frame is completed. These relationships are configured in the GetTaskCollection using the Dependency property.
Updated task dependencies
To ensure proper sequencing in the construction project, the following changes were made to task predecessors:
- Survey Land now starts after Site Preparation (Predecessor = “1FS”).
- Install Steel Frame follows Framing (Predecessor = “7FS”).
- Electrical Wiring begins after Interior Work (Predecessor = “10FS”).
- Interior Work starts once Install Roof is complete (Predecessor = “9FS”).
- Existing valid dependencies like Excavation (2FS) and Framing (6FS) were retained.
- All tasks now have clearly defined predecessors, eliminating any missing or empty values for better clarity and scheduling accuracy.
Predecessor validation
To prevent scheduling errors, Syncfusion provides built-in validation for predecessors. For example, if a user attempts to set a circular dependency (e.g., “Task A → Task B → Task A”), the Gantt chart will flag the issue, ensuring the schedule remains feasible. Enable validation by setting AllowTaskbarEditing=”true” and testing dependencies during user interactions.
Customizing dependency rendering
Syncfusion customization options enhance dependency visualization, ensuring clear and professional timelines for stakeholder presentations.
Customizing connector lines
Connector lines help visualize task dependencies, especially critical ones like the Finish-to-Start (FS) link between Pour Footings (Task 5) and Cure Footings (Task 6). To style these lines, use inline CSS targeting .e-connector-line and .e-connector-line-arrow classes. Although the Gantt component provides attributes like ConnectorLineBackground and ConnectorLineWidth, inline CSS offers more precise control over styling. This flexibility allows you to override default styles and ensure consistent rendering across different environments.
The following code snippets demonstrate both approaches, using inline CSS and component attributes, to customize connector lines effectively:
Inline CSS example:
@using Syncfusion.Blazor.Gantt
<SfGantt DataSource="@TaskCollection" Height="550px" Width="100%" RenderBaseline="true">
</SfGantt>
<style>
.e-connector-line {
stroke: #ab6060fc !important; /* Red for critical FS dependencies */
stroke-width: 2px !important; /* Line thickness */
}
.e-connector-line-arrow {
fill: #ab6060fc !important; /* Matches arrow color */
}
</style>
Component attribute example:
@using Syncfusion.Blazor.Gantt
<SfGantt
DataSource="@TaskCollection"
Height="550px"
Width="100%"
RenderBaseline="true"
ConnectorLineBackground="#ab6060fc"
ConnectorLineWidth="2">
...
...
</SfGantt>
Why it matters: Customized connector lines enhance stakeholder communication by visually distinguishing critical dependencies, such as Cure Footings (Task 6) to Framing (Task 7), reducing misinterpretation and highlighting key milestones.
Taskbar customization
To improve the visual clarity of task dependencies in construction projects, the Syncfusion Blazor Gantt Chart allows developers to apply custom templates to taskbars. This customization helps highlight specific types of dependencies, such as Finish-to-Start (FS), by using distinct colors or styles. For example, FS-dependent tasks like Pour Footings can be color-coded to make them stand out from others, enabling stakeholders to quickly identify critical paths and understand the sequencing of tasks.
Why it matters: This visual differentiation enhances the overall readability of the project timeline and supports better communication among teams.
The following code snippet demonstrates how to use a taskbar template to apply conditional styling based on the presence of a predecessor:
Code example:
<SfGantt DataSource="@TaskCollection" Height="450px" Width="1000px">
<GanttTaskFields
Id="TaskId"
Name="TaskName"
StartDate="StartDate"
Duration="Duration"
Dependency="Predecessor"
ParentID="ParentId">
</GanttTaskFields>
<GanttTemplates TValue="TaskData">
<TaskbarTemplate>
@{
var task = context as TaskData;
<div class="e-gantt-child-taskbar e-gantt-child-taskbar-inner-div"
style="background-color: @(task.Predecessor != null ? "#6d619b" : "#d3d3d3");height: 16px;">
<span>@((context as TaskData).TaskName)</span>
</div>
}
</TaskbarTemplate>
</GanttTemplates>
</SfGantt>
Tooltip customization
The Syncfusion Blazor Gantt Chart supports tooltip customization, allowing you to display dependency information directly within the chart interface. By configuring tooltips to show predecessor values, teams can instantly understand task relationships without needing to inspect the full schedule manually. For example, when hovering over the Install Roof task, the tooltip can display its dependency as 2FS+3d, indicating it starts three days after Install Steel Frame finishes.
Why it matters: This immediate visibility helps reduce miscommunication and ensures that all stakeholders are aligned.
The following code snippet demonstrates how to customize tooltips to show predecessor details using the ConnectorLineTemplate:
Code example:
<SfGantt DataSource="@TaskCollection" Height="450px" Width="1000px">
<GanttTaskFields
Id="TaskId"
Name="TaskName"
StartDate="StartDate"
Duration="Duration"
Dependency="Predecessor"
ParentID="ParentId">
</GanttTaskFields>
<GanttTooltipSettings ShowTooltip="true" TValue="TaskData">
<ConnectorLineTemplate>
<div>Predecessor: @((context as TaskData).Predecessor)</div>
</ConnectorLineTemplate>
</GanttTooltipSettings>
</SfGantt>
Best practices for predecessor configuration
- Ensure logical sequencing (e.g., “Pour Footings” → “Cure Footings”).
- Use offsets wisely for delays or overlaps.
- Avoid circular dependencies.
- Leverage parent-child relationships.
- Enable interactive editing with AllowTaskbarEditing.
Example configuration
Below is an updated GetTaskCollection method with corrected and complete predecessor values for a community center construction project. Each task has a logical predecessor to ensure proper sequencing and address gaps in the original configuration (e.g., missing or empty predecessors).
For further information, please refer to our GitHub repository sample.

Conclusion
The Syncfusion Blazor Gantt Chart transforms construction project management by simplifying task dependencies. From FS to SF relationships, hierarchical coordination, and delay visualization, it empowers teams to build accurate, dynamic schedules.
Explore the Syncfusion Blazor Gantt Chart documentation for more details. If you’re a Syncfusion user, you can download the setup from the license and downloads page. Otherwise, you can download a free 30-day trial.
You can also contact us through our support forum, support portal, or feedback portal for queries. We are always happy to assist you!
Related Blogs
- Blazor Gantt Chart Update: Timezone Scheduling, WBS Codes & Excel-Style Filtering
- Blazor Scheduler vs. Gantt Chart: Which is Right for Your Project?
- What’s New in Blazor Gantt Chart: 2024 Volume 3
- Seamlessly Switch Between Project and Resource Views in the Blazor Gantt Chart
This article was originally published at Syncfusion.com.
Top comments (0)