When undertaking a brownfield development, industrial de-commissioning or removal of underground storage tanks, the removal of the contaminated soils can pose logistical and regulatory issues. Once the contaminated soils are removed you need to remove large amounts of heavy materials, without causing any cross contamination, dust and transporting it in accordance with federal legislation.
Due to variety of contamination present in soils (petroleum, heavy metals, Volatile Organic Compounds and industrial solvents) all soils will need to be properly classified and contained under EPA and Department of Transportation (DOT) guidelines.
By following the correct steps below you can safely and legally remove the contaminated soil:
Soil Classification and Approval
Before any soil is loaded into your trailer you must classify the soil.
Composite & Spot Sampling
Sample soils in grids throughout the excavation area to determine if soils are regulated as hazardous (RCRA) or non-hazardous industrial waste. This will include testing for TCLP metals, VOCs, SVOCs and total petroleum hydrocarbons.
Waste Profile Approval
Submit sample packs to an authorised landfill (Subtitle C for hazardous or Subtitle D for non-hazardous). This will give you approval of your Waste Profile.
Segregation
Ensure that the clean soil is separated from the contaminated areas on site using a lined stockpile pad.
Containment Requirements
If you are transporting contaminated soils on public roads you must ensure you have the correct heavy duty equipment to stop any leakage or particulate.
Requirements:
Heavy duty bladders and sealed tailgates. If you are transporting wet or sludgy soils you must ensure your dump trailer/roll off has heavy mil bladders and sealed tailgates.
Secure tarps. All soils must be securely covered with a watertight tarp.
Loader Monitoring. Ensure loader bucket weights are monitored to avoid any overweight issues on the highway.
Manifest
Large remediation jobs can have dozens of trucks a day and it is vital that you keep records.
Manifests:
All trucks must have a Uniform Hazardous Waste Manifest or Non-Hazardous Waste Bill of Lading. The waste codes and generator details must match the approved Waste Profile.
Synchronised Dispatch:
Ensure truck turnaround times match excavation times to avoid any queueing on local community or municipal roads.
Scale Tickets:
Ensure all weights leaving site match the approved scale tickets from the disposal site.
Final Thoughts
To successfully remediate the site you must work with the excavation team, environmental engineers and authorised transport providers. By obtaining waste profiles early, ensuring all soils are securely contained and matching all loads from pit to landfill you can ensure your remediation schedule is met and avoid any environmental risk.
For more information on authorised hazardous waste transport please visit Envirotest Transport.