A mood board can make herringbone and chevron look like two names for the same angled floor. The order document should not. Herringbone is built from rectangular blocks turned at right angles to one another. Chevron uses angled ends cut to meet along a continuous axis. That difference changes the drawing, the machining questions, the border detail, and the way installers count cut pieces.

HUAGE’s custom sizing records separate eight herringbone rows, H01 to H08, from seven chevron rows, C01 to C07. The records are a reference for scale and thickness. They do not approve a particular room layout, stock position, or waste allowance. A buyer still needs to connect the selected row to a CAD plan and a factory-confirmed construction.

Start With Block Shape, Not the Pattern Name

The herringbone schedule runs from 610 × 75 mm at H01 to 910 × 190 mm at H08. Intermediate formats include 610 × 93 mm, 610 × 125 mm, 760 × 125 mm, 760 × 155 mm, 910 × 125 mm, and 910 × 155 mm. All eight rows record 15 mm total thickness with 3.0, 4.0, or 5.0 mm wear-layer options.

The chevron schedule starts at 510 × 75 mm for C01 and reaches 780 × 190 mm for C07. It also includes 510 × 95 mm, 510 × 125 mm, 680 × 125 mm, 680 × 155 mm, and 780 × 155 mm. These rows also record 15 mm total thickness and 3.0, 4.0, or 5.0 mm wear-layer options.

The dimensions should be read as independent fields. A 610 × 95 mm block tells the designer its plan size. It does not tell the buyer whether the top layer is 1.2 mm or 3.0 mm, nor does it establish the species. For example, legacy catalogue item PDF-21 records American black walnut herringbone at 610 × 95 × 15 mm with either a 1.2 mm or 3.0 mm wear layer. PDF-22 records a 500 × 90 × 15 mm chevron with a 3.0 mm layer. Neither record should be silently merged into a custom C-row specification.

Draw the Axis and the Repeat

A herringbone plan should show the rectangular block, the turn direction, the starting line, and the way the pattern terminates at each wall. A chevron plan should show the angled ends, the V-axis, and the point where each run begins. “Follow the room” is not enough information for a quantity takeoff.

The centreline matters because a small drafting change can move the cut pattern across an entire room. The drawing revision should therefore appear on the sample approval and on the quantity schedule. If the architect rotates the pattern to align with a doorway or window, the revised repeat should be reviewed before the order is locked.

Borders deserve their own line. A design may run the pattern to the skirting, stop it against a narrow frame, or combine both in different zones. The order should identify whether the border is part of the patterned module or a separate plank line. HUAGE’s P08 row records 1200 × 75 × 15 mm with 3.0, 4.0, or 5.0 mm wear-layer options, but using that row as a border still requires a project detail and quantity.

Ask How Left and Right Machining Will Be Supplied

Both patterns can involve left and right tongue-and-groove configurations. The need and ratio should come from the approved layout and the factory’s machining proposal, not from a blanket rule that every carton must be split equally. Some layouts may consume equal numbers of handed blocks. Others may need a different balance because of alcoves, borders, or starting conditions.

The purchase order should state whether separate L and R bundles are required, how each bundle is identified, and how unmatched quantities will be handled. It should also state the packing unit. A carton count without the number of blocks per carton cannot prove that enough handed pieces are on site.

This is where herringbone and chevron documentation often diverges. A rectangular herringbone block may use a repeating right-angle module, while a chevron run depends on clean mitred joints along its axis. Both need accurate dimensions, but the installation drawing should not substitute one geometry for the other.

Calculate Cuts From the Actual Room

A flat waste percentage is a weak basis for a patterned floor. The quantity should begin with the verified field area, the module repeat, the border zones, and the perimeter cuts. Historic walls, columns, and door openings can interrupt the repeat in ways that a simple rectangle does not show.

The CAD takeoff should distinguish usable field modules from cut pieces and should record whether offcuts can be reused. It should also separate the field material from the border and from any transition pieces. Combining them into one square-metre figure makes it difficult to check the correct dimensions, finish, and batch at delivery.

Where the layout requires balanced handed pairs, calculate the required pair count before rounding cartons. The detailed method belongs in a calculation file linked to the drawing revision. It should not be inferred from the total area alone.

Put Five Items on the Approval Sheet

A useful pattern order brings five references together. The first is the approved visual sample, including species, colour, knots, and surface. The second is the selected H or C row with length, width, total thickness, and wear layer written separately. The third is the CAD revision showing axis, repeat, borders, and handed machining. The fourth is the quantity calculation with packing units. The fifth is the batch and sample identification that will follow the goods to site.

Two source issues deserve an explicit pending flag. H04 contains a repeated 15 in the legacy text, while H07 and H08 use an uncertain separator after total thickness. C02 contains the malformed wear-layer string 3.074.0/5.0. The cleaned readings are plausible, but they remain confirmation items. An automated import should preserve the raw value and block final approval until a person resolves it.

Keep the Site Check Connected to the Order

Before installation, the project team should verify substrate flatness, moisture, damp isolation, connections, movement clearances, and edge details. The installation method must match the product documents. Underfloor heating, where proposed, needs written confirmation for the exact build and system rather than a general assumption about engineered flooring.

When cartons are first opened, multiple boxes should be laid out together so colour and grain variation can be distributed against the approved sample. The record should identify any substituted row, changed border, or different batch before adhesive is applied. That simple link between drawing, sample, and delivered goods is more useful than a pattern name on its own.

Review the Sample at Pattern Scale

A single block shows timber, machining, and finish, but it does not show the full repeat. The approval package should include a layout sample or drawing at the intended module size. It should show the starting point, the turn or mitre, the border, and at least one termination at a wall.

This review catches differences that disappear in a close-up. A narrow line in a small sample may become a dominant joint across a room. A colour contrast that looks subtle on one block may repeat strongly in a two-species module. The designer should approve the pattern and the timber together rather than signing them as unrelated items.

For mixed-species or mixed-material parquet, the sample record should identify each component. HUAGE’s A-21 record combines North American black walnut and Canadian maple, so the approval should describe both timbers and the intended contrast. For an inlaid module, the insert material and its position need the same clarity.

The drawing should also state what happens when the room dimension does not fit a complete repeat. The border may absorb the remainder, or the field may need a cut module. That decision should be made before the quantity is released. Leaving it to the installer changes both the appearance and the count of usable pieces.

HUAGE’s public specification reference is

https://huagefloors.com/en/captured/specification.html

It is a starting point for these questions, not a replacement for the project-specific order confirmation.

Top comments (0)