A website redesign project plan template needs six phases in a fixed order: audit, content, design, build, QA and launch. Each phase ends with a sign-off before the next one starts. That one rule prevents most late, over-budget redesigns. Below is the plan as we run it, with the checks at each stage, so you can copy it for your own project or a client's.

Why redesigns run late

Most redesigns do not fail on design. They fail on order.

A common pattern looks like this. Someone opens a design tool on day one. Mockups get approved with placeholder text. Then the real copy arrives, and it does not fit. Pages get redesigned. The build starts while content is still moving. Nobody lists the old URLs, so links from search results and other sites break at launch. Testing happens on the live site, by visitors.

None of this needs a bigger team or a better tool. It needs a plan where each phase has a clear input, a clear output and one person who says yes.

What a good website redesign project plan template covers

When we wrote this plan down, we checked it against four questions:

  • Does each phase have a finished output? An audit sheet, a content list, approved designs, a staging site, a test report, a live site.
  • Is there a gate between phases? A named person approves the output before work moves on.
  • Are the risky parts listed early? Old URLs, forms, third-party scripts and cookies are the things that break quietly.
  • Does it work at any size? The same order applies to a five-page brochure site and a large store. Only the length of each phase changes.

The plan does not fix durations. Scope, content readiness and how fast approvals come back decide that. What it fixes is the order.

Website redesign timeline, phase by phase

  • Phase 1: Audit: List every page, URL, form, script and cookie. Note what gets visits and what is already broken.
  • Phase 2: Content: Decide which pages stay, merge or go. Write or collect final copy before design starts.
  • Phase 3: Design: Design the key page types with real content, on desktop and phone, then get one sign-off.
  • Phase 4: Build: Build from approved designs, or adapt a template. Map every old URL to a new one.
  • Phase 5: QA: Test widths, forms, keyboard use, speed, cookies and each redirect on a staging copy.
  • Phase 6: Launch: Deploy, recheck forms and analytics on the live site, and watch for missing pages.
  • After launch: Fix what real visitors find, then close the project with a short handover note. ## The plan, step by step
  1. Audit the current site. Crawl or click through every page and put each URL in a sheet. Add columns for page type, owner, keep or drop, and notes. List every form and where it sends data. List every third-party script: analytics, chat, maps, embeds, ad pixels. If you have visitors in the UK or EU, note which scripts set non-essential cookies, because those need consent under GDPR rules. The output is one sheet everyone agrees on.

  2. Settle the content. Go through the sheet and mark each page as keep, rewrite, merge or delete. Write the new sitemap. Then collect or write the final copy for the main page types. Final does not mean perfect. It means the length and structure will not change. Design with real text from here on.

  3. Design with real content. Design the page types, not every page. A home page, a standard content page, a listing page and a contact page cover most sites. Show each one on a phone width as well as desktop. Check text contrast and focus states here, while changes are cheap. The output is one approved set of designs and one sign-off, not a running conversation.

  4. Build. Build from the approved designs only. New ideas go on a list for after launch. This is also where you decide between a custom build and a template. A template can save weeks if its pages already match your sitemap. If you go that way, check the licence covers client sites, as explained in our licence post. Before the build is done, write the redirect map: every old URL from the audit points to its new home, so no visitor or search result lands on a missing page.

  5. QA on staging. Test on a staging copy, never the live site. Work from a written list. We test several screen widths, tap targets and font sizes, as in our mobile-friendly checklist. Submit every form and confirm the message arrives. Tab through each page with a keyboard. Turn on reduced motion and check nothing breaks. Load the site with a clean browser and confirm no non-essential cookie is set before consent. Click every redirect in the map. If the site is a JavaScript project, a clean production build is part of QA:

npm install
npm run build
Enter fullscreen mode Exit fullscreen mode
  1. Launch. Pick a quiet time and have the person who can roll back available. Deploy or switch DNS. Then repeat the short version of QA on the live site: forms, analytics, redirects, consent banner. Watch for missing-page errors over the first days and add redirects as they appear.

How we run it

AIVCJ is a small studio: one lead developer plus an AI build pipeline, and a person reviews every product before it ships. The same shape applies to client work. The pipeline helps with the repetitive parts, such as building URL lists, drafting redirect maps and running test passes. A person makes every decision at the gates and signs off each phase.

We learned the value of a written QA list the hard way. When we set up our own template zips as a buyer would, small things broke that nobody had seen from the inside. We wrote that up in what broke when we set up our templates. That is why QA in this plan is a list, not a feeling.

No gates Gate after each phase
Design starts before copy exists, so layouts get redone Copy is settled before design, so layouts fit real text
Old URLs vanish and visitors land on missing pages Every old URL is mapped to a new one before launch
Testing happens on the live site QA runs on staging against a written list
Old cookie scripts carry over without anyone checking Scripts and cookies are listed in the audit and kept on purpose

This plan does not include a brand strategy phase or user research. If your redesign needs either, add it before the audit. It also does not replace legal advice on privacy. It only makes sure the cookie and consent questions get asked early.

What you have at the end, and what to do next

If you follow the six phases, you finish with more than a new site. You have an audit sheet of what existed, a content list of what changed, approved designs, a redirect map and a test report. That paper trail makes the next change much easier, and it answers the client who asks why a page moved.

To start today, copy the timeline above into your project tool as six milestones. Name one approver for each. Then open a sheet and begin the audit with every URL on the current site. That step alone surfaces most of the surprises.

How long does a website redesign take?

It depends on the number of page types, how ready the content is and how fast approvals come back. This plan fixes the order of work, not the length of each phase.

Can I use a template instead of a custom build?

Yes, in the build phase. Check that its pages match your new sitemap first. Every Pulse product has one licence that covers unlimited sites, including client sites.

Where do cookies and GDPR fit in the plan?

List every script and cookie in the audit. Decide what stays in the build. In QA, confirm no non-essential cookie is set before consent for UK and EU visitors.

Why design with real content instead of placeholder text?

Real copy changes layouts. Designing with it once avoids redoing approved pages when the final text arrives.
If you would rather hand the whole plan to someone else, from audit to launch, you can tell us about your project. We will run it in the order above, with a person signing off each phase.