When multiple projects need the same people, assigning tasks one project at a time can hide conflicts and capacity gaps. A resource schedule helps by comparing planned work with people’s available time across a selected period.
A practical review starts with the planning period, known project allocations, working hours, and unavailable time. Then check the plan from both project and individual perspectives before committing to additional work. A schedule supports forecasting; it does not replace detailed task assignments for day-to-day delivery.
Build a useful resource plan
Resource scheduling is the practice of planning people’s capacity across projects over a selected period. The plan should distinguish confirmed work from assumptions about potential projects and unassigned roles.
- Allocations: planned blocks of time for a person or placeholder on a project. They can include total hours and hours by day.
- Placeholders: unnamed, role-based resources for planning before a specific person is assigned.
- Tentative projects: a way to model potential work and examine its demand before confirming the project.
- Unavailable time: periods when a team member cannot be scheduled, such as paid time off or public holidays.
- Working hours: the length of day set in a user’s profile, which establishes their daily capacity.
Keeping these inputs visible makes it easier to review the assumptions behind a staffing decision. Use placeholders when the role is known but the person is not, and keep unconfirmed work tentative rather than treating it as a commitment.
Review demand from two perspectives
Start with projects
A project view groups allocations by project. Use it to review planned staffing and time across project timelines, or to consider how allocations relate to project budgets. Grouping allocations by role can make a project-level plan easier to scan.
Then check people
A people view groups allocations by person. It helps managers review individual workloads and spot potential conflicts across projects. Grouping by person is useful when the decision is about an individual’s capacity.
In Teamwork Schedule, the People view is available on Optimize and Enterprise plans; legacy Scale plans may also include it. Choose the view and grouping that match the decision you need to make.
Interpret schedule metrics carefully
Metrics describe the selected period and depend on the inputs in the plan. Check the dates and underlying allocations before using them to make a staffing decision.
Allocation usage
Allocation usage compares logged time with allocated hours:
allocation usage percentage = logged time ÷ allocated hours
Use it to compare recorded work with the time reserved for that work.
Allocation roll-up
An allocation roll-up is the total allocated hours for a project or person during the selected period. It combines allocations that fall within that range.
Availability
Availability is the capacity left after accounting for unavailable time and allocated hours:
capacity remaining = length of day − (unavailable time + allocated hours)
The length of day comes from the person’s profile working hours, so profile settings affect this calculation.
Billable allocation and potential revenue
A billable allocation is marked as billable so it can contribute to profitability and revenue insights. Potential revenue is calculated as:
potential revenue = Σ(user billable rate × billable allocated hours)
Treat this as a forecast based on allocation and rate inputs, not as confirmed revenue.
Review capacity before confirming work
- Choose the period the team needs to plan.
- Add or review allocations for known project work.
- Check unavailable time and profile working hours.
- Switch between project and people views to inspect demand from both perspectives.
- Review available insights for capacity, budget usage, and forecast financial impact.
- Adjust the plan or staffing assumptions before confirming additional work.
This sequence separates confirmed commitments from potential projects and makes the assumptions behind capacity decisions easier to inspect.
Check access and insight availability
In Teamwork Schedule, site admins can view and manage allocations, unavailable time, placeholders, and tentative projects. Standard users’ access depends on their profile permissions and project membership.
- Access resource scheduling: lets users view the Schedule and allocations for people on projects they belong to.
- Manage resource scheduling: lets users create and edit allocations on projects they belong to.
Before rollout, confirm that planners have the management permission and other team members can review the relevant allocations. Availability of Insights depends on the subscription plan, so verify that the required information is available to your team.