AI models take months. Grid connections take 61 months.

A Nature Sustainability study published Nov 16 counted 403 US hyperscale data centers using about 1.8% of US electricity, and every new megawatt they add waits years in the connection queue. A new AI model generation takes weeks to months; a new grid connection took a median of 61 months in 2025. The binding constraint on the AI buildout has moved from capital to electricity, and the people who run the grid now co-set the pace of the race.

TL;DR

  • New power takes years to connect while model generations take months.
  • Two ways around the queue: co-location, blocked by FERC 2-1 for Amazon's Susquehanna expansion, and a contracted nuclear restart for Microsoft targeting 2028.
  • Virginia, Oregon, Ohio and Iowa hold over half of hyperscale use, and your state utility commission's docket shows whether large-load cases are coming.

Data center electricity demand through 2028

The Department of Energy announced a report from Lawrence Berkeley National Laboratory (LBNL): US data centers of all types used 4.4% of US electricity in 2023, with 6.7-12% projected for 2028. The 1.8% covers hyperscale sites only, from a 2024-25 satellite count; the 4.4% is a 2023 estimate for every type.

Virginia, Oregon, Ohio and Iowa hold over half of hyperscale use. For someone choosing where new capacity lands, new power must clear the interconnection queue, the list of projects waiting to connect to the grid.

Interconnection queue times and requests

That queue runs on a different clock:

Clock Time it runs on
Model generation weeks to months
New grid connection median 61 months in 2025, up from 22 in 2008

Synergy Research estimates total US data center capacity doubles in three years, 36 months against a median of 61 to connect new power.

A plan built on 2008's 22-month median is off by more than three years.

At the end of 2025, US queues held 2,061 GW of requests against 1,374 GW of installed US capacity. About 1 in 5 projects that requested a connection from 2000 to 2020 had reached commercial operation by the end of 2025, so getting in line is not a plan: the power that arrives is far smaller than the 2,061 GW request pile.

PJM paused review of new requests from 2022 until 2026. CAISO accepted no new requests in 2024 or 2025.

Money is not the bottleneck. Anthropic's IPO filing records a $26.0 billion private placement, yet the compute it buys needs power that sits in the same queue.

FERC's order on Amazon's Susquehanna co-location

One way around the queue is co-location, a data center drawing power directly from a plant. On Nov 1, 2024, the Federal Energy Regulatory Commission (FERC) voted 2-1 to reject an agreement that would have raised Amazon's co-located load at the Susquehanna nuclear plant from 300 to 480 MW. Commissioner Mark Christie said co-location raises "complicated, nuanced, and multifaceted issues." FERC decides how much co-located load a plant can serve, so its sign-off comes ahead of any hyperscale operator's power plan.

Microsoft's Three Mile Island restart

Microsoft took a contract route instead of co-location. On Sept 20, 2024, it signed a 20-year power purchase agreement, a long-term contract for a plant's output, to restart Three Mile Island Unit 1 (the Crane Clean Energy Center), targeting 2028, with all output going to Microsoft.

Our read: contracting an existing plant's output skips a multi-year queue request and gives Microsoft dedicated power on a timeline it controls.

Local opposition and siting

In the Nov 2026 midterms, voters in 40 of 41 local ballot initiatives nationwide voted to limit or prevent data center development. That is a third constraint on siting, after the queue and FERC: a lab picking a site has to price in local opposition.

Checking large-load cases in your state

Try this:

  1. Search your state public utility commission's online docket for "data center" rate cases.
  2. Note the docket numbers and hearing dates on any entries.
  3. If nothing appears, try "large load" or "interconnection".
  4. Ask the commission's docket clerk which large-load cases are open.

A hit looks like this: Docket No. [XXXX-XX], hearing [date].

Regional backlog: LBNL Queued Up 2026 report (West 567 GW, ERCOT 408 GW).

What to watch next

Watch how fast PJM's backlog moves once its pause ends. Watch the FERC Order 2023 rollout: every transmission provider is implementing the reforms, and LBNL says the effects will not be immediate. Watch each co-location ruling after the 2-1 Susquehanna order for how far FERC's veto reaches. Until those move, electricity is the binding constraint on the AI buildout, and grid operators, regulators and local voters co-set the pace of the race.

Dan writes the AI explainers on super-intelligence.rocks, where this piece first appeared.