Project planning is a crucial component for the successful execution of any project, be it a website, a product development or a management task. Sufficient planning would involve breaking down all the tasks to be handled and estimating the time you would take in completing each of them. But this isn't necessarily an easy task to do!
That's where PERT comes in. PERT - which is short for Program Evaluation and Review Technique - is a project management technique that involves predicting task durations based on three separate duration estimates as opposed to a single estimate or guess. https://projecttimecalculator.com/pert-calculator/
What is PERT Estimation?
PERT calculation considers three different values for the tasks: Optimistic; Pessimistic; and Most Likely.
The longest realistic time the job should take.
The specified time that a task will probably take when performed normally.
Pessimistic estimate (P): The upper time limit within which the task will be completed when faced with unforeseen difficulties.
With these three estimates, project managers will be able to plan a schedule more realistically and help plan for delay.
How to Calculate Expected Project Time
The PERT formula is simple and gives more weight to the most likely estimate.
Expected Time = (O + 4M + P) ÷ 6
A website development project can be estimated with three values: an optimistic estimate of 5 days, a most likely estimate of 8 days, and a pessimistic estimate of 17 days.
Using the formula:
Expected Time = (5 + 4 × 8 + 17) ÷ 6
Expected Time = 54 ÷ 6 = 9 days.
This is an estimate of the length of time it will take for team members to complete a specific task.
Why Is PERT Important for Project Managers?
Project managers are regularly faced with uncertain time frames for completing projects, evolving expectations for project deliverables and unexpected difficulties during the life cycle of a project. PERT (Program Evaluation Review Technique) provides a method of reducing the uncertainty associated with developing a schedule for a project through the development of numerous estimates.
This software helps teams determine which tasks require additional time, allocate resources more efficiently, and make better decisions regarding project deadlines. It is especially beneficial for projects that include multiple sequential tasks.
A PERT (program evaluation and review technique) calculator can help you calculate the expected time for a project to be completed, its variability, the standard deviation of its completion time, and how likely it is that you will finish the project before your deadline.
Estimation Techniques that Improve Projects Schedules
In developing timelines for projects, realistic estimates should always be considered. There is no need to make estimates under the assumption of idealistic situations. It's important to think about the possible problems, availability of necessary resources, and complexity of tasks to be accomplished.
The splitting up of a large task into manageable small parts can assist with the estimate as well. After all of the manageable small parts have been estimated for the amount of time required to accomplish them, then the total will give you the estimate of completing the large task.
Conclusion
PERT (Program Evaluation & Review Technique) may be a great tool for project managers in developing better schedules and dealing with uncertainty of project deadlines. After making an evaluation of the best, the most probable, and the worst case scenarios, the project manager can get a better schedule and be closer to meeting project deadlines.
There would be much more organization and effectiveness in project management if there were proper estimation techniques and identifying of potential unknowns.