DEV Community

Dov at HireDov
Dov at HireDov

Posted on

"Lead time: 30 days" — what your supplier actually means, and how to plan around it

A supplier tells you the lead time is 30 days. You mark a date on the calendar 30 days from today and plan a launch around it. This is how many first production runs end up late without anyone technically lying.

"Lead time" is one of the most loosely used words in sourcing. Before you build a plan on it, find out which clock the supplier is using.

1. Ask when the clock starts

Thirty days from what? Common answers include:

  • from the purchase order
  • from receipt of the deposit
  • from approval of the pre-production sample
  • from approval of artwork or final files
  • from arrival of raw materials or components

Each one can add days or weeks before production really begins. Ask the supplier to name the trigger in writing, e.g. "30 days from deposit received and artwork approved."

2. Ask when the clock stops

"Done" can mean finished goods, packed goods, goods ready for pickup at the factory, or goods loaded on a vessel. None of those is "in your warehouse." Match the stop point to the Incoterm on the quote: an EXW or FOB quote usually ends at the factory or port, and everything after is your timeline.

3. Build the full timeline yourself

Write the steps out, one line each, with an owner and an estimate:

  1. Quote accepted and PO issued
  2. Deposit paid and confirmed
  3. Artwork / files approved
  4. Pre-production sample made, shipped, approved
  5. Materials ordered and received
  6. Production
  7. Inspection (yours or a third party's), plus time to fix issues
  8. Packing and booking freight
  9. Transit
  10. Customs clearance
  11. Inland delivery and receiving

The supplier's "30 days" is often only step 6. The rest is the part that surprises people.

4. Watch for the calendar

Factories have holidays, peak seasons and capacity crunches. If your order lands during a busy period or right before a long shutdown, the same 30 days can stretch. Ask directly: "Is there any holiday or capacity constraint between now and the ship date?"

5. Put it in the PO

Once you agree on the trigger, the stop point and the date, write them into the purchase order along with what happens if the date slips (a revised date, notification within X days, or a remedy you both accept). It keeps the conversation factual if things move.

6. Compare lead times like you compare prices

When you collect several quotes, add three columns: lead time, clock start, clock stop. A supplier quoting 25 days from sample approval may be slower than one quoting 35 days from PO. Without the start and stop points, the numbers are not comparable.

A simple rule of thumb

Treat the first lead time a new supplier gives you as an estimate for one step, not as your delivery date. Build the full timeline, add buffer for samples and inspection, and confirm it in writing.


I work on HireDov, an AI procurement agent that contacts suppliers, requests and follows up on quotes, and lays them side by side, including lead time terms. If that is useful: https://hiredov.com

Top comments (0)