Buyers spend weeks on the specification and then accept whatever inspection pack turns up with the pipe. On a thin-wall, large-diameter section the inspection pack is where the arguments actually happen, because the wall has so little margin and the seam is so long that both dimensional and NDT records have to be read as a set.
Here is the one-page sheet I would ask any mill to complete before the pipe leaves. It is short, it is easy to audit, and it removes most of the ambiguity that shows up three months later on site.
1. Dimensional record taken in one position
Four wall readings at 0°, 90°, 180° and 270° on the same section, taken after the pipe has settled on its saddles. Plus the ovality figure with the instrument named, and a single line saying whether it was taken before or after the hydrostatic test. A number without the instrument and the timing is not a record, it is a claim.
For a 3 m section with an 8 mm wall, a 0.5 % ovality allowance is 15 mm. That is big enough to matter for fit-up and big enough that "measured" and "estimated with a tape" should not be treated as the same data point. If you are buying large-diameter thin-wall alloy steel welded pipe, this is the first line I would insist on.
2. RT coverage expressed as a length, not a count
Coverage rules are written as a percentage of seam length. On a long longitudinal seam that produces a lot of films, and the practical questions are which sections were shot, whether the ends and the restart points are included, and who interpreted them. Ask for the film map rather than the film count. A pack that says "20 % RT" tells you nothing about where the 20 % was taken.
3. Hydrostatic test: pressure, hold time, and drying
Pressure and hold time should match the standard in the order, and the chart or log should be attached. The part people forget is drying. A 3000 mm section holds a lot of water and dries slowly, and residual moisture inside a thin-wall pipe is a corrosion start point, not a cosmetic issue.
4. The MTC fields that actually matter
Heat number, plate heat number, product analysis, tensile and bend results, and the measured wall — not the nominal wall. The traceability chain has to run from the pipe back to the plate, otherwise the certificate is decoration. EN 10204 3.1 certificates are the normal route for export orders, and the difference between 3.1 and 2.2 is exactly whether an independent inspector signed it.
5. How the pipe will be packed and lifted
Not an inspection item in the standard, but it decides whether the dimensional sheet is still true on arrival. Saddles, end caps, lashing points, and the maximum length that inland transport will accept. If the transport limit is 12 m and the spool is 15 m, the shop needs to know before it starts, not after.
Putting it on one page
Five columns: item, requirement, method, result, witness. One page per section, signed. It costs the mill half a day and it saves both parties a claim.
Shiwang Pipe runs JCOE sections to 3000 mm and joins to 5000 mm by circumferential seam where transport allows; the inspection sheet above is the one we use on those orders.