Hi all.
I always get into confusion, when client wants to know the budget and time for the project.
Any suggestions please.
Thanks
For further actions, you may consider blocking this person and/or reporting abuse
We're a place where coders share, stay up-to-date and grow their careers.
Hi all.
I always get into confusion, when client wants to know the budget and time for the project.
Any suggestions please.
Thanks
For further actions, you may consider blocking this person and/or reporting abuse
Stephen Solka -
Snigdha Mathur -
Rafik Naccache -
Agbanusi John -
Once suspended, herawais will not be able to comment or publish posts until their suspension is removed.
Once unsuspended, herawais will be able to comment and publish posts again.
Once unpublished, all posts by herawais will become hidden and only accessible to themselves.
If herawais is not suspended, they can still re-publish their posts from their dashboard.
Discussion (1)
First you have to find out the micro task and it's completion time.
Suppose, If you have 100 task. Every task needs to complete 4 hour. So 100 tasks need 100*4=400 hour.
Now 400/8 = 50 days. Here 8 is working hour in a day.
So if you use 1 developer it needs 50 days/2 month. Think if you pay him $400, so it's actual development cost is $400*2=$800,
Now add your profit with this.