65% of IT projects are delayed.
People say "couldn't help it."
But one company reduced delay rate from 65% to 15%.
The secret was Critical Chain (CCPM) methodology.
Problems with Traditional Approach
The problem is adding individual buffers to all tasks.
Task A (5 days + 3 day buffer) → Task B (3 days + 2 day buffer) → Task C (4 days + 3 day buffer)
= Total 20 days
Why is this a problem?
Do you know Parkinson's Law? "Work expands to fill the time available."
Give 3 days buffer to a 5-day task, and all 8 days will be used.
Even if finished early, won't move to next task. "We have time anyway" and work slowly.
CCPM Innovation
Remove individual buffers and place integrated buffer at project end.
Task A (5 days) → Task B (3 days) → Task C (4 days) → [Project Buffer 4 days]
= Total 16 days (20% shorter!)
Looks simple but the effect is amazing.
Implementation Method
def calculate_ccpm_schedule(tasks):
"""Calculate CCPM schedule"""
# Aggressive estimates (50% probability)
aggressive_estimates = []
for task in tasks:
# Traditional: Includes safety margin (90% probability)
conservative = task["estimate"]
# CCPM: 50% probability of completion
aggressive = conservative * 0.6
aggressive_estimates.append({
"name": task["name"],
"duration": aggressive
})
# Project buffer (50% of total)
total_duration = sum(t["duration"] for t in aggressive_estimates)
project_buffer = total_duration * 0.5
return {
"tasks": aggressive_estimates,
"buffer": project_buffer,
"total": total_duration + project_buffer
}
A 40-day project becomes 30 days.
Buffer Management is Key
Must check daily how buffer is being used.
function checkBufferStatus(projectProgress, bufferConsumed) {
const ratio = bufferConsumed / projectProgress;
if (ratio < 0.6) {
return '🟢 Safe: Normal progress';
} else if (ratio < 1.0) {
return '🟡 Warning: Root cause analysis needed';
} else {
return '🔴 Danger: Immediate action needed';
}
}
If project is 50% done but only 30% buffer used, it's safe.
If 50% done but 70% buffer used? Danger signal.
Real Application Case
A story from a mid-size IT company.
Before: Traditional Method
- Project duration: 6 months expected
- Actual completion: 8.5 months
- Delay: 2.5 months (42%)
- Buffer efficiency: 40% (mostly wasted)
After: CCPM Applied
- Project duration: 4.5 months expected
- Actual completion: 4.8 months
- Delay: 0.3 months (7%)
- Buffer efficiency: 85%
CCPM Introduction Steps
Week 1: Understanding and Preparation
Monday: Learn CCPM concepts (2 hours)
Tuesday: Analyze current project
Wednesday: Identify critical chain
Thursday: Calculate buffer size
Friday: Team training and agreement
Week 2: Pilot Application
Start with a small project.
Reduce 10 tasks, 4-week project to 3 weeks.
Check buffer consumption daily, analyze weekly.
Week 3-4: Expansion and Optimization
Analyze pilot results and apply to entire project.
Common Mistakes and Solutions
Mistake 1: Buffer Too Small
# ❌ Wrong example
buffer = total_duration * 0.2 # 20% is too small
# ✅ Appropriate buffer
if project_uncertainty == "high":
buffer = total_duration * 0.7 # 70%
elif project_uncertainty == "medium":
buffer = total_duration * 0.5 # 50%
else:
buffer = total_duration * 0.3 # 30%
Mistake 2: Allowing Multitasking
If one developer does 3 tasks simultaneously, productivity drops to 40%.
Doing one at a time maintains 90% productivity.
Mistake 3: Not Monitoring Buffer
class BufferMonitor:
def daily_check(self, progress, buffer_used_today):
"""Check daily"""
self.consumed += buffer_used_today
consumption_rate = self.consumed / self.total_buffer
if consumption_rate > progress * 1.5:
self.alert("🔴 Excessive buffer consumption!")
return ["Root cause analysis", "Additional resource input", "Review scope adjustment"]
CCPM Success Factors
1. Management Support
CCPM requires changing existing mindset.
Need culture of "not blaming individual task delays but looking at entire project."
2. Accurate Measurement
Buffer consumption rate must be measured daily, task completion rate too.
3. Culture Change
Important culture of immediately moving to next when finished early.
Expected Effects
Properly applying CCPM:
- Project duration: -25%
- Delay rate: 65% → 15%
- Buffer efficiency: 40% → 85%
- Team stress: Greatly reduced
- Prediction accuracy: 2x improvement
Conclusion
CCPM looks simple but is powerful.
The key is removing individual buffers, integrating into project buffer, and thorough monitoring.
"Impossible schedule" becomes "possible schedule."
Try it in your next project.